PMP Project Management Professional v2020
PMP Project Management Professional v2020
How it works
- • One question per screen, at your own pace
- • No time limit
- • Instant feedback right after each question
- • Explained review of every question
- • Free, no account needed
Quiz details
- Topic
- Tecnologia
- Questions
- 499
- Time
- No time limit
- Author
- Dutton Training
- Updated on
- 10/12/2026
- Subjects
- Geral
Question preview
Check the first 10 questions. Answers are revealed only when you take the quiz.
1 · Geral
An element of the project scope statement is: https://vceplus.com/
- A)Acceptance criteria.
- B)A stakeholder list.
- C)A summary budget,
- D)High-level risks.
2 · Geral
Which document describes the necessary information to determine if a project is worth the required investment?
- A)Cost baseline
- B)Service level agreement
- C)Memorandum of understanding
- D)Business case
3 · Geral
Which input to the Plan Risk Management process provides information on high-level risks?
- A)Project charter
- B)Enterprise environmental factors
- C)Stakeholder register
- D)Organizational process assets
4 · Geral
Which item is an example of personnel assessment?
- A)Resource calendar
- B)Tight matrix
- C)Team-building activity
- D)Focus group
5 · Geral
Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?
- A)Procurement documents
- B)Communications plan
- C)Project charter
- D)Stakeholder register
6 · Geral
In which Knowledge Area is the project charter developed?
- A)Project Cost Management
- B)Project Scope Management
- C)Project Time Management
- D)Project Integration Management
7 · Geral
The ability to influence cost is greatest during which stages of the project?
- A)Early
- B)Middle
- C)Late
- D)Completion
8 · Geral
Which process involves developing an approximation of the monetary resources needed to complete project activities?
- A)Estimate Costs
- B)Control Costs
- C)Determine Budget
- D)Plan Cost Management
9 · Geral
Which tool or technique is used in the Develop Project Management Plan process?
- A)Pareto diagram
- B)Performance reporting
- C)SWOT analysis
- D)Expert judgment
10 · Geral
The organization's perceived balance between risk taking and risk avoidance is reflected in the risk:
- A)Responses
- B)Appetite
- C)Tolerance
- D)Attitude
And 489 more questions waiting for you.
How to study with this quiz
Simulate the real exam
Set aside uninterrupted time and answer as if it were exam day, respecting the time limit.
Learn from mistakes
In the review, focus on the questions you missed and understand why the correct answer is right.
Retake to consolidate
Retake the quiz periodically to reinforce concepts and track your progress in retaining the content.