PRINCE2 Foundation

200 questões60 min9 visualizaçõespor Dutton Training

Certification dumps PRINCE2 Foundation

Como funciona

  • • Uma questão por tela, no seu ritmo
  • • Tempo total de 60 minutos
  • • Correção na hora, logo depois de cada questão
  • • Revisão comentada de cada questão
  • • Grátis, sem precisar criar conta

Ficha técnica

Tema
Tecnologia
Questões
200
Tempo
60 min
Autor
Dutton Training
Atualizado em
28/10/2026
Assuntos
Geral

Prévia das questões

Confira os enunciados das primeiras 10 questões. O gabarito aparece apenas ao fazer o simulado.

  1. 1 · Geral

    Which product records any project outcomes perceived as negative by stakeholders?

    • A)Business Case
    • B)Project Plan
    • C)Communication Management Strategy
    • D)Project Product Description
  2. 2 · Geral

    What is the definition of a project outcome?

    • A)A measurable improvement that is perceived as an advantage by one or more stakeholders
    • B)The reason for the project
    • C)The result of the change derived from using the project's outputs
    • D)The project's specialist products.
  3. 3 · Geral

    Which is NOT a purpose of a Benefits Review Plan?

    • A)Define the period over which the cost-benefit analysis will be based
    • B)Describe how to measure the performance of the project's products in operational use
    • C)Define the scope, timing and ownership of the benefit reviews required
    • D)Describe how to measure and confirm any benefits that are to be realised after the project is closed
  4. 4 · Geral

    Which product documents the information needed to demonstrate continued business justification?

    • A)Business Case
    • B)Communication Management Strategy
    • C)Project Product Description
    • D)Quality Management Strategy
  5. 5 · Geral

    Which is NOT a purpose of a Benefits Review Plan?

    • A)Define the period over which the cost-benefit analysis will be based
    • B)Describe how to measure the performance of the project's products in operational use
    • C)Define the scope, timing and ownership of the benefit reviews required
    • D)Describe how to measure and confirm any benefits that are to be realised after the project is closed
  6. 6 · Geral

    What is an off-specification?

    • A)A new requirement
    • B)A quality tolerance
    • C)A type of issue
    • D)A major risk
  7. 7 · Geral

    Which is a type of issue?

    • A)A lesson
    • B)A request for change
    • C)An Exception Report
    • D)A risk with an estimated high impact
  8. 8 · Geral

    Which is a typical core activity within configuration management?

    • A)Quality assurance
    • B)Risk management
    • C)Verification and audit
    • D)Progress reporting
  9. 9 · Geral

    Which is a typical core activity within configuration management?

    • A)Issue management
    • B)Quality inspection
    • C)Identification
    • D)Preparation
  10. 10 · Geral

    What needs to be in place to ensure effective issue and change control?

    • A)Configuration management system
    • B)Manage by exception
    • C)Quality planning
    • D)Information needs for stakeholders

E mais 190 questões esperando por você.

Como estudar com este simulado

Simule a prova real

Reserve um momento sem interrupções e responda como se estivesse no dia da prova, respeitando o tempo.

Aprenda com os erros

Na revisão, concentre-se nas questões que errou e entenda por que a alternativa correta é a certa.

Refazer para consolidação

Refaça o simulado periodicamente para fixar os conceitos e acompanhar sua evolução na retenção dos conteúdos.